Building Progress
Building Progress

 

 

 

 

CURRENT STAGE: FOUNDATION

March 2017

Crews completed the grading process on the 9.5-acre property adjacent to the main WSC campus in early February 2017. As a result of this work, one sees a dramatic difference between the before and after photos of the property. Since the completion of grading, crews have been installing underground wet utilities. It was fitting that this wet utilities work was conducted during the wettest season in recent years around Southern California. In late March, foundation work will begin. This stage of the student housing project consists of the installation of underground dry utilities (i.e., electrical, cable, telephone), digging footings, installation of rebar, pouring slabs, and creating roads and curbs.

Check back soon for regularly updated photos!

 

 

 

foundation

 

 

GRADING